Investor Appendix

Supporting detail behind the donor case: capital plan by phase, revenue build by stream, scenario assumptions, risk register, governance, and reporting cadence. Numbers reconcile to the liveFinancials page.

A. Capital plan by phase

PhaseWindowThesisBase capex
P1Months 1–12Design, permits, recording studio, 200-seat intimate recital hall shell, and 3-classroom wing. Classes + studio billing from month 6.$2.45M
P2Months 13–24Recital hall + classrooms OPEN. Ticketed series begins, fundraising events launch. Operating break-even target.$1.60M
P3Months 49–60600-seat outdoor amphitheater + spatial-audio sacred dome + acoustic hall upgrade. Funded by operating surplus + secondary capital campaign.$3.08M
P4Months 25–36TV/Radio + podcast wing (extension of studio building). Tandon Distinguished Chair recruited once ops can carry the salary.$1.05M
Total (escalated @ 5%)$9.03M

B. Line-item capex

ItemPhaseYearAmount
Architectural design, permits, civil & site prepP1Y1$350K
Recording studio (build + gear)P1Y1$450K
Classroom wing — 3 rooms + black-box rehearsalP1Y1$750K
Recital hall (200-seat) — shell & foundationP1Y1$900K
Recital hall — envelope, acoustic interior, MEPP2Y2$850K
Recital hall — seating, FF&E, A/V, finishesP2Y2$350K
Livestream / broadcast rigP2Y2$180K
Opening-season programming runwayP2Y2$220K
TV/Radio studio build-out (extension of studio bldg)P4Y3$650K
Podcast suites + control room (2 booths)P4Y3$220K
Tandon Distinguished Chair — recruitment & setupP4Y3$180K
Outdoor Pine Lake amphitheater (600-seat)P3Y5$1.40M
Spatial-audio sacred-sound dome (build + system)P3Y5$950K
Recital hall acoustic upgrade + riggingP3Y5$380K
Construction contingency (8%) + commissioningP3Y5$350K

C. 5-year operating projection (base case)

YearRevenueCostsNet opsCapexTranche inCum cash
Y1$503K$583K$-80060$2.45M$1.50M$-1030060
Y2$2.08M$1.42M$661K$1.68M$1.50M$-549467
Y3$3.72M$2.33M$1.38M$1.16M$1.50M$1.18M
Y4$5.00M$2.89M$2.11M$0$1.50M$4.79M
Y5$6.63M$3.60M$3.03M$3.74M$1.50M$5.57M

Operating break-even: Year 2.

D. Key assumptions

  • Lead pledge: $7.5M paid in 5 equal annual tranches of $1.50M. The pledge was re-sized from an initial $5M after modeling showed a $1.16M Y1 cash gap against $2.45M of Phase-1 capex; flat $1.5M tranches shrink the Y1 gap to roughly $660K (closed by end of Y2) and keep cumulative cash positive from Y3 onward.
  • Cost escalation: 5% per year applied to capex from Y2 onward.
  • Class economics: $450/month × 2 sessions × 8-week cohorts; ramp from 5 sections in Y1 to 24 by Y5.
  • Hall opens end of Y2; first full ticketed season in Y3.
  • Tandon Chair deferred to Y3 to preserve Y1–Y2 runway.
  • Amphitheater + spatial-audio dome funded from retained surplus in Y5, not from the lead gift.

E. Risk register

RiskLikelihoodImpactMitigation
Construction cost overrunMediumHigh10% escalation reserve; phased build defers $3.7M to Y5
Class enrollment shortfallMediumMediumTemple-network marketing; corporate L&D and afterschool channels
Artistic director recruitment delayLowMediumPart-time interim in Y2; full search Y3
Major donor concentrationHighHighActive prospect pipeline of 36 named families + foundations
Hall utilization < 60%LowMediumRental, streaming, and rehearsal-block revenue absorbs gap
Regulatory / 501(c)(3) timingLowLowFiscal sponsorship via HUA during interim

F. Governance & reporting

  • Center operates as a program within HUA's 501(c)(3); separate restricted fund accounting.
  • Donor-named Advisory Council with quarterly review of financials and programming.
  • Annual audited financials; semi-annual narrative + KPI report to the lead donor.
  • Tranche release tied to milestones: design complete, classroom wing CO, hall opening, etc.